SAFE WORK PROCEDURE

SWP-017

SUSPENDED LOADS

If it is in the air, the zone is alive.

DOCUMENT
GOSPEL-SWP-017
REVISION
01 CURRENT
EFFECTIVE
2026-09-01
OWNER
GOSPEL Safety
APPROVED BY
GOSPEL
REVIEW
2027-09-01

PURPOSE

Keep people out from under a load and keep loads from hanging unattended.

SCOPE

Any time a load is off the ground on a lift under this program.

This document is the method — the steps. Hazards, consequence and residual risk for the same work are in the JHA library. A procedure is not a hazard analysis. A hazard analysis is not a procedure.

PROCEDURE

  1. 01

    ZONE BEFORE HOIST

    The fall zone is cleared and held before the load leaves the ground.

  2. 02

    WHILE IT IS UP

    Nobody walks under. Nobody uses the shadow as a shortcut.

  3. 03

    ATTENDED

    A named operator remains with the crane, or the load is landed. Convenience is not a reason to hang steel.

  4. 04

    WEATHER

    Wind rising: land or hold to the plan.

  5. 05

    LAND

    Prepared set. Stable before anyone goes in to disconnect.

RESPONSIBILITIES

This program

The published method for the work. Stop-work is named in it. It does not own the site.

Supervisor

Confirms the plan, the crew, the zone and the stop criteria. Owns whether the hook moves.

Crane operator

Runs only the machine they are competent on, to the chart, after inspection. Stops on an unclear signal or a broken plan.

Rigger

Selects, inspects and applies the hitch. Does not guess weight, centre of gravity or angle.

Signalperson

One set of hands on the crane. Holds the zone. STOP means stop.

Worker

Works to this program and to site rules — whichever is stricter. Uses the three rights. Reports damaged gear.

REQUIRED COMPETENCY

  • Entire crew briefed on the zone

EQUIPMENT

  • Zone marking
  • Tag lines

PPE

  • Hard hat
  • CSA-grade footwear
  • High-visibility clothing
  • Eye protection
  • Task-rated gloves
  • Hearing protection where required
  • Fall protection where the work exposes a fall

PROHIBITED PRACTICES

  • Standing under a suspended load
  • Leaving a load hanging over a walkway
  • Riding the load

EMERGENCY RESPONSE

Stop the lift. Make people safe. Land or hold the load if it can be done without a second incident. First aid. Notify the site and the employer. Hold the scene.

DOCUMENTATION

  • FLHA
  • Pre-use / inspection record
  • This SWP number and revision

REFERENCES

  • Workers Compensation Act s. 21 — known or reasonably foreseeable hazards; instruction and supervision
  • OHS Regulation (B.C. Reg. 296/97, in force 15 Apr 1998) Part 3 — OHS program, instruction, inspections
  • OHS Regulation Part 4 s. 4.13 — risk assessment where rescue or evacuation may arise
  • OHS Regulation Part 8 — PPE; headwear CSA Z94.1-05 or Z94.1-15
  • OHS Regulation Part 11 — fall protection
  • OHS Regulation Part 14 — Cranes and Hoists
  • 14.2(5) — CSA Z150-1998, or ASME B30.5-2004, or ASME B30.22-2005 (articulating boom)
  • 14.2(6) — CSA Z248-2004 for tower, hammerhead and self-erecting tower cranes
  • 14.35 pre-use inspection · 14.36 load weight · 14.42.1 critical lift · 14.44 loads over work areas · 14.45 unattended loads · 14.47–14.49 signals
  • OHS Regulation Part 15 — Rigging
  • Manufacturer load chart, manual and configuration limits
  • Site lift plan, FLHA and site rules where stricter

PROVENsin(). Current version on this site.