SAFE WORK PROCEDURE

SWP-007

STANDARD HAND SIGNALS

Standard signals. Not a private dialect.

DOCUMENT
GOSPEL-SWP-007
REVISION
01 CURRENT
EFFECTIVE
2026-09-01
OWNER
GOSPEL Safety
APPROVED BY
GOSPEL
REVIEW
2027-09-01

PURPOSE

Use the hand signals the crew agreed, the ones the Board authorizes, so the operator is not translating.

SCOPE

Lifts under this program using hand signals. Combined with radio on blind or noisy lifts as briefed.

This document is the method — the steps. Hazards, consequence and residual risk for the same work are in the JHA library. A procedure is not a hazard analysis. A hazard analysis is not a procedure.

PROCEDURE

  1. 01

    AGREE

    The signal set is confirmed in the brief. Site-specific extras are named, not assumed.

  2. 02

    POSITION

    Signalperson where the operator can see both the hands and, as far as the lift allows, the load.

  3. 03

    ONE MOVEMENT

    One signal at a time. Hoist, boom, swing, stop — not a dance.

  4. 04

    EMERGENCY STOP

    Both arms out, unmistakable. Operator stops. No interpretation.

  5. 05

    TRANSFER

    If the signalperson must move, the operator is told. The crane waits through the transfer.

RESPONSIBILITIES

This program

The published method for the work. Stop-work is named in it. It does not own the site.

Supervisor

Confirms the plan, the crew, the zone and the stop criteria. Owns whether the hook moves.

Crane operator

Runs only the machine they are competent on, to the chart, after inspection. Stops on an unclear signal or a broken plan.

Rigger

Selects, inspects and applies the hitch. Does not guess weight, centre of gravity or angle.

Signalperson

One set of hands on the crane. Holds the zone. STOP means stop.

Worker

Works to this program and to site rules — whichever is stricter. Uses the three rights. Reports damaged gear.

REQUIRED COMPETENCY

  • Signalperson who can demonstrate the signals
  • Operator who will not invent meanings

EQUIPMENT

  • Gloves the operator can see

PPE

  • Hard hat
  • CSA-grade footwear
  • High-visibility clothing
  • Eye protection
  • Task-rated gloves
  • Hearing protection where required
  • Fall protection where the work exposes a fall

PROHIBITED PRACTICES

  • Invented signals
  • Signalling from a pocket
  • Signalling while also rigging the hitch

EMERGENCY RESPONSE

Stop the lift. Make people safe. Land or hold the load if it can be done without a second incident. First aid. Notify the site and the employer. Hold the scene.

DOCUMENTATION

  • FLHA
  • Pre-use / inspection record
  • This SWP number and revision

REFERENCES

  • Workers Compensation Act s. 21 — known or reasonably foreseeable hazards; instruction and supervision
  • OHS Regulation (B.C. Reg. 296/97, in force 15 Apr 1998) Part 3 — OHS program, instruction, inspections
  • OHS Regulation Part 4 s. 4.13 — risk assessment where rescue or evacuation may arise
  • OHS Regulation Part 8 — PPE; headwear CSA Z94.1-05 or Z94.1-15
  • OHS Regulation Part 11 — fall protection
  • OHS Regulation Part 14 — Cranes and Hoists
  • 14.2(5) — CSA Z150-1998, or ASME B30.5-2004, or ASME B30.22-2005 (articulating boom)
  • 14.2(6) — CSA Z248-2004 for tower, hammerhead and self-erecting tower cranes
  • 14.35 pre-use inspection · 14.36 load weight · 14.42.1 critical lift · 14.44 loads over work areas · 14.45 unattended loads · 14.47–14.49 signals
  • OHS Regulation Part 15 — Rigging
  • Manufacturer load chart, manual and configuration limits
  • Site lift plan, FLHA and site rules where stricter