sin()
PROVEN

SAFE WORK PROCEDURE

SWP-026

LOCKOUT / ISOLATION

If you are not operating it, the energy is isolated. Part 10.

DOCUMENT
GOSPEL-SWP-026
REVISION
01 CURRENT
EFFECTIVE
2026-09-01
OWNER
GOSPEL Safety
APPROVED BY
GOSPEL
REVIEW
2027-09-01

PURPOSE

Keep a person off stored energy — hoist, slew, luff, travel, hydraulics, electrical — when the work is service, inspection beyond pre-use, rescue, or anything that puts a body in the machine.

SCOPE

Workers on a crane they are not operating: maintenance they are assigned, climbing past the cab for inspection, rescue, or working on tools and vehicles used on the lift. Not a substitute for the owner’s lockout procedure on that crane. Not tower jumping — see GOSPEL-SWP-027.

This document is the method — the steps. Hazards, consequence and residual risk for the same work are in the JHA library. A procedure is not a hazard analysis. A hazard analysis is not a procedure.

PROCEDURE

  1. 01

    NAME THE WORK

    What is being done, on which machine, which energy. If you cannot name it, you are not isolating it.

  2. 02

    OWNER’S PROCEDURE

    Use the lockout written for this crane when it exists. This procedure does not override a stricter owner procedure.

  3. 03

    ISOLATE AND LOCK

    Controls off. Energy isolated. Personal lock and tag. One person, one lock. Do not lend a key.

  4. 04

    VERIFY

    Try to start. Confirm the hoist, slew and luff will not move. Residual hydraulic or raised jib — released or blocked as the manufacturer says.

  5. 05

    WORK, THEN REMOVE YOUR LOCK

    Do the work. Remove only your lock. If the job runs past a shift, the handover of locks is a procedure — not a text message.

RESPONSIBILITIES

This program

The published method for the work. Stop-work is named in it. It does not own the site.

Supervisor

Confirms the plan, the crew, the zone and the stop criteria. Owns whether the hook moves.

Crane operator

Runs only the machine they are competent on, to the chart, after inspection. Stops on an unclear signal or a broken plan.

Rigger

Selects, inspects and applies the hitch. Does not guess weight, centre of gravity or angle.

Signalperson

One set of hands on the crane. Holds the zone. STOP means stop.

Worker

Works to this program and to site rules — whichever is stricter. Uses the three rights. Reports damaged gear.

REQUIRED COMPETENCY

  • Understands this machine’s isolation. Follows the owner’s lockout where it exists. Does not invent a padlock on a live hoist.

EQUIPMENT

  • Personal lock
  • Tag
  • The owner’s lockout devices for this crane

PPE

  • Hard hat
  • CSA-grade footwear
  • High-visibility clothing
  • Eye protection
  • Task-rated gloves
  • Hearing protection where required
  • Fall protection where the work exposes a fall

PROHIBITED PRACTICES

  • Reaching into a machine that can still hoist
  • Sharing a lock because ‘we’re both on it’
  • Bypassing a limit to ‘just inch it’ during service

EMERGENCY RESPONSE

If energy appears during the work: get clear. Re-isolate. Do not finish the job on a live machine.

DOCUMENTATION

  • Owner lockout for this serial
  • GOSPEL-FRM-002 / 027 if the machine was down for a defect

REFERENCES

  • Workers Compensation Act s. 21 — known or reasonably foreseeable hazards; instruction and supervision
  • OHS Regulation (B.C. Reg. 296/97, in force 15 Apr 1998) Part 3 — OHS program, instruction, inspections
  • OHS Regulation Part 4 s. 4.13 — risk assessment where rescue or evacuation may arise
  • OHS Regulation Part 8 — PPE; headwear CSA Z94.1-05 or Z94.1-15
  • OHS Regulation Part 11 — fall protection
  • OHS Regulation Part 14 — Cranes and Hoists
  • 14.2(5) — CSA Z150-1998, or ASME B30.5-2004, or ASME B30.22-2005 (articulating boom)
  • 14.2(6) — CSA Z248-2004 for tower, hammerhead and self-erecting tower cranes
  • 14.35 pre-use inspection · 14.36 load weight · 14.42.1 critical lift · 14.44 loads over work areas · 14.45 unattended loads · 14.47–14.49 signals
  • OHS Regulation Part 15 — Rigging
  • Manufacturer load chart, manual and configuration limits
  • Site lift plan, FLHA and site rules where stricter

PROVENsin(). Current version on this site.