SAFE WORK PROCEDURE
CRANE COMMUNICATION
If the operator cannot hear or see the signal, the crane does not move.
- DOCUMENT
- GOSPEL-SWP-005
- REVISION
- 01 CURRENT
- EFFECTIVE
- 2026-09-01
- OWNER
- GOSPEL Safety
- APPROVED BY
- GOSPEL
- REVIEW
- 2027-09-01
PURPOSE
Make communication a control, not a courtesy.
SCOPE
All lifts under this program. Hands, radio, or both. Dedicated systems where Part 14 requires them.
This document is the method — the steps. Hazards, consequence and residual risk for the same work are in the JHA library. A procedure is not a hazard analysis. A hazard analysis is not a procedure.
PROCEDURE
- 01
NAME THE SIGNALPERSON
One person. Transfer is spoken and acknowledged.
- 02
AGREE THE SYSTEM
Standard hand signals and/or radio protocol. Channel, call signs, STOP.
- 03
TEST
Before the load. If it fails in the test, it will fail in the hole.
- 04
DURING THE LIFT
Operator moves only on a clear signal. Signalperson watches load, path and zone.
- 05
LOSS
Any break: stop. Resume only after the crew is reset.
RESPONSIBILITIES
This program
The published method for the work. Stop-work is named in it. It does not own the site.
Supervisor
Confirms the plan, the crew, the zone and the stop criteria. Owns whether the hook moves.
Crane operator
Runs only the machine they are competent on, to the chart, after inspection. Stops on an unclear signal or a broken plan.
Rigger
Selects, inspects and applies the hitch. Does not guess weight, centre of gravity or angle.
Signalperson
One set of hands on the crane. Holds the zone. STOP means stop.
Worker
Works to this program and to site rules — whichever is stricter. Uses the three rights. Reports damaged gear.
REQUIRED COMPETENCY
- Signalperson competency
- Operator who will not guess
EQUIPMENT
- Radios as specified
- High-visibility gloves for hand signals
PPE
- Hard hat
- CSA-grade footwear
- High-visibility clothing
- Eye protection
- Task-rated gloves
- Hearing protection where required
- Fall protection where the work exposes a fall
PROHIBITED PRACTICES
- Two people signalling
- “He knows what I mean”
- Music or chatter on the lift channel
EMERGENCY RESPONSE
Stop the lift. Make people safe. Land or hold the load if it can be done without a second incident. First aid. Notify the site and the employer. Hold the scene.
DOCUMENTATION
- FLHA
- Pre-use / inspection record
- This SWP number and revision
REFERENCES
- Workers Compensation Act s. 21 — known or reasonably foreseeable hazards; instruction and supervision
- OHS Regulation (B.C. Reg. 296/97, in force 15 Apr 1998) Part 3 — OHS program, instruction, inspections
- OHS Regulation Part 4 s. 4.13 — risk assessment where rescue or evacuation may arise
- OHS Regulation Part 8 — PPE; headwear CSA Z94.1-05 or Z94.1-15
- OHS Regulation Part 11 — fall protection
- OHS Regulation Part 14 — Cranes and Hoists
- 14.2(5) — CSA Z150-1998, or ASME B30.5-2004, or ASME B30.22-2005 (articulating boom)
- 14.2(6) — CSA Z248-2004 for tower, hammerhead and self-erecting tower cranes
- 14.35 pre-use inspection · 14.36 load weight · 14.42.1 critical lift · 14.44 loads over work areas · 14.45 unattended loads · 14.47–14.49 signals
- OHS Regulation Part 15 — Rigging
- Manufacturer load chart, manual and configuration limits
- Site lift plan, FLHA and site rules where stricter