JOB HAZARD ANALYSIS

JHA-006

MOBILE CRANE SETUP

Punch-through, short-rig, tail swing, overhead lines, wrong chart.

DOCUMENT
GOSPEL-JHA-006
REVISION
01 CURRENT
EFFECTIVE
2026-09-01
OWNER
GOSPEL Safety
APPROVED BY
GOSPEL
REVIEW
2027-09-01

THE JOB

Putting a mobile crane or boom truck on the ground the chart requires. Method: GOSPEL-SWP-001, 021, 022. 14.2(5) CSA Z150-1998 or ASME B30.5-2004 or B30.22-2005.

WHO IS EXPOSED

  • Operator
  • Oiler / second
  • People in the jack line or tail-swing arc
  • Anyone under a boom being raised into lines

A JHA names what can hurt someone and how that risk is controlled. It is not the procedure. Do the work to the matching SWP. WorkSafeBC does not prescribe a JHA form — the Workers Compensation Act s. 21(2)(b) requires workers to be made aware of known or reasonably foreseeable hazards. This is how GOSPEL does that for this job.

HAZARDS AND RISK

Task is the work being analysed — not a procedure to follow. Controls follow the hierarchy: eliminate, substitute, engineer, administer, PPE last. The badge is how bad this task going wrong is in this job. Extreme is the killer with no recovery. High is serious injury or a dropped load you still have a chance to stop. Moderate is lost time or a plan that failed. Low is first aid.

LOWMODERATEHIGHEXTREME

TASKHAZARDRISKCONTROL
Confirm the machineCounterweight, boom, software or tyres not as assignedHIGHChart does not apply. Overload without an alarm that matches reality. 14.2, 14.12.Serial, configuration and chart are the same machine. Manufacturer instructions in the cab.
Walk the padBackfill, vaults, slope, buried services, other cranesEXTREMEPunch-through, overturn, contact with a main. High severity.Look and ask. Locates. Engineer when the surface is a guess. Mats spread load — they do not invent bearing.
Outriggers and matsShort-rig without that chart; undersized cribbing; people in the jack lineEXTREMEOverturn. Crush beside a jack. 14.2 to the manufacturer.Fully extended unless the short-rig chart is in the cab and in use. People clear while jacking. Level within manufacturer limit.
Swing and linesTail swing, boom into plant, overhead electricalEXTREMEStruck-by, arc, step potential. 14.40, 14.52.1.Swing check before the hook. MAD as a wall. Spotter when the boom can encroach.
Inspect, then liftDefect that affects lifting, skipped pre-useMODERATEFunction failure on the first pick. 14.35.Pre-use this shift, this configuration. Lifting defects: crane down.

RESIDUAL RISK

Ground that looked competent can still give on the first load. Residual is settlement and a crane that is no longer the crane on the chart. Held by mats sized for the reaction, a level check, and treating the first load as a test of the pad. 14.11 support structure. 14.35 pre-use.

THE JOB DOES NOT PROCEED IF

  • Wrong configuration for the chart in the cab
  • Ground will not hold the reaction
  • Outriggers not in the charted position
  • Overhead lines inside MAD

PPE — LAST LINE

  • Hard hat
  • CSA-grade footwear
  • High-visibility clothing
  • Eye protection
  • Task-rated gloves
  • Hearing protection where required
  • Fall protection where the work exposes a fall

SWP — MOBILE CRANE SETUP →

REFERENCES

  • Workers Compensation Act s. 21(2)(b) — workers made aware of known or reasonably foreseeable hazards
  • Workers Compensation Act s. 21(2)(e) — information, instruction, training and supervision
  • OHS Regulation B.C. Reg. 296/97 (in force 15 Apr 1998) Part 3 — program, instruction, inspections (ss. 3.1–3.12)
  • CCOHS Job Safety Analysis — JSA and JHA are the same method: break the job, name the hazards, select controls
  • Workers Compensation Act s. 21 — known or reasonably foreseeable hazards; instruction and supervision
  • OHS Regulation (B.C. Reg. 296/97, in force 15 Apr 1998) Part 3 — OHS program, instruction, inspections
  • OHS Regulation Part 4 s. 4.13 — risk assessment where rescue or evacuation may arise
  • OHS Regulation Part 8 — PPE; headwear CSA Z94.1-05 or Z94.1-15
  • OHS Regulation Part 11 — fall protection
  • OHS Regulation Part 14 — Cranes and Hoists
  • 14.2(5) — CSA Z150-1998, or ASME B30.5-2004, or ASME B30.22-2005 (articulating boom)
  • 14.2(6) — CSA Z248-2004 for tower, hammerhead and self-erecting tower cranes
  • 14.35 pre-use inspection · 14.36 load weight · 14.42.1 critical lift · 14.44 loads over work areas · 14.45 unattended loads · 14.47–14.49 signals
  • OHS Regulation Part 15 — Rigging
  • Manufacturer load chart, manual and configuration limits
  • Site lift plan, FLHA and site rules where stricter