BINDER FORM
FRM-044FRM-044
THARRP / HIGH-ANGLE RESCUE COVER
Who requested the survey, which fire department, how to summon them. Not a fall-protection plan.
- TYPE
- FORM
- DOCUMENT
- PROVEN-FRM-044
- STATUS
- CURRENT
- REVISION
- 01
- EFFECTIVE
- 2026-09-01
- OWNER
- Proven
- APPROVED BY
- Proven
- REVIEW
- 2027-09-01
WHEN
Before a tower operator goes up. After a change of crane location or expected duration past 60 days on a high-rise.
CAPTURE
- Site and crane
- Who requested the THARRP survey (host / prime / owner)
- Fire department named
- Portal confirmation / survey date
- Formal Site Survey on site if past 60 days
- How the operator summons rescue
- Confirmation date
ROUTING
Host or prime owns the portal request. The supervisor or the employer confirms before the lift. Copy in the binder.
PROVEN. Current version on this site.