PRE-ASSEMBLY MEETING

The meeting before the tower or self-erect goes up. Named people, sequence, zone, abort.

TYPE
FORM
DOCUMENT
PROVEN-FRM-036
STATUS
CURRENT
REVISION
01
EFFECTIVE
2026-09-01
OWNER
Proven
APPROVED BY
Proven
REVIEW
2027-09-01

FILL THIS FORM →

WHEN

Before erect, climb, reposition or dismantle. Before the assist crane is on load.

CAPTURE

  • Site, date, crane make / model / serial
  • Activity (erect, climb, reposition, dismantle)
  • Activity supervisor and lead hand
  • Crew and assist-crane operator
  • Sequence and hold points
  • Exclusion zone and public interface
  • Radios and stop word
  • Weather abort
  • Rescue / THARRP named
  • Attendance and signatures

ROUTING

Activity supervisor runs it. Copy in the site binder. Copy with the NOP-TC file.