What Your Crane Crew Should Know Before They Arrive
If the first time they see the machine, the load and the site is when they park, you have already spent the briefing.
sin() · 4 AUG 2026 · 1 MIN
SHARE
A note that says 'crane and rigger, Tuesday, downtown' is not a brief. It is a calendar entry. The crew will invent the rest on site, and you will not like some of the inventions.
Before anyone starts, they need the work, the site, the machines and the dates. Before they arrive, they get the hazards and the procedure. Guessing is not a brief.
SEND THIS BEFORE THE GATE
- Machine: make, model, configuration, and who owns it.
- Load: weight, dimensions, lifting points, and whether any of that is still a guess.
- Site: access, ground, overhead, public interface, other trades.
- Signals: radio or hand, who has the right to stop.
- Hours, PPE, site rules, and the person who actually owns the lift.
If you cannot tell who is coming and what they are walking into, you are not ready to start.
A good crew will still walk the lift when they arrive. The brief does not replace eyes. It means they are not using the walk to discover that the crane is a different class, the load is double, or the pick is over a live sidewalk.
If you want people at 7:00, send the facts the day before. If the facts change at 6:15, say so. Silence is not a plan.
THE WIRE
—
Say it on the record. Replies, likes, the floor talking — like a jobsite channel, not a comments box.
LOADING THE WIRE…
THE WIRE
GET
THE WIRE.
New stories on crane safety, rigging and the people doing the work.